1 · The work order

Read the work order. The simulation stays locked for now. First you need to understand what the job is.

Work order no. 2026-B-084

CustomerThe Schneider family PropertyDetached house, built 1978, bathroom on the 1st floor (2.40 m × 2.80 m) HistoryFull bathroom renovation three months ago. The old acrylic shower tray was removed and replaced by a level-access walk-in shower, 1.20 m × 1.00 m, with a linear drain and large-format tiles. Complaint"Since the renovation, the shower water runs almost to the bathroom door during a normal shower. The hallway smells musty, and there are dark damp marks on the ceiling of the guest toilet below." FindingsBuild-up height from structural slab to finished floor level (FFL): only 85 mm. Slope in the shower area: 0.5 %. Rain shower head: 18 l/min. Moisture at the lower screed edge: 98 digits (saturated).

Your task

Find out which mistakes were made during installation and explain how build-up height, slope and waterproofing are connected. Plan the correct build-up and the checks on site. At the end, explain to the Schneider family in three sentences what happened.

2 · Your prediction

Commit to an answer before you use the simulation. Wrong predictions are allowed. They are exactly what you learn the most from.

3 · Explore

Work in pairs: one person operates the simulation, the other takes notes. Tasks tick off automatically as soon as you reach the required state. Time-lapse: while the shower runs, one second equals about one week of use.

  • E1 · Normal condition. Set standard conditions: build-up height 105 mm, slope 2.0 %, waterproofing 100 %. Turn the shower on. Watch drainage and moisture.
  • E2 · Find the limit. What is the minimum slope at which water from a running shower just reaches the drain without overflowing?
    %
  • E3 · Recreate the damage. Set up the Schneider case: build-up height 85 mm, slope 0.5 %, waterproofing 40 %. Let the shower run for weeks. When does anyone notice the damage?
  • E4 · Counter-check. At full build-up height, set an excessive slope of 3.0 %. What does that mean for the tiling and for the user?

4 · Formulate the rule

First compare your prediction with what the simulation showed. Then write the rules yourself. You will only see the model rule afterwards.

QuestionYour predictionThe simulation shows

Model rule

Slope: A level-access shower needs a continuous slope of 1.5 to 2.0 % towards the drain. Only then does surface water drain reliably without backing up. Too much slope (above approx. 2.5 %) causes a slip hazard, trip edges and a lot of cutting waste with large-format tiles.

Waterproofing: Tiles and cement grout are not waterproof by design. Underneath, there must be continuous bonded waterproofing, with the sealing collar embedded without voids and undamaged sealing tapes. Every defect lets water into the screed and insulation with every shower. The damage only becomes visible after weeks, and by then it is permanent.

Build-up height: The drain with trap, the pipe fall and the minimum screed cover all need space. If the build-up height is too low, people save on slope or on screed cover. The results are overflow, cracks above the pipe and creeping moisture damage. Solution: choose a flat renovation drain system; never save on slope or waterproofing.

Where does your rule differ? Add to it above before you move on.

5 · To the workbench

Now the real component counts. The simulation is locked, because it does not replace a single minute of craft.

a) Work plan: put the steps in the right order

    b) Measure on the practice build-up or on site

    Measure and enter the values. No build-up available? Your teacher will give you values.

    MeasurementValue

    6 · Feedback

    Your real measurements go back into the simulation. Would this build-up survive daily showering?

    MeasurementValueRating

    "Check" loads the value into the simulation, sets all other values to target, rebuilds the shower area and starts the shower. That way you see the effect of exactly this one value.

    Solution: work order no. 2026-B-084

    Cause: The build-up height of 85 mm was not enough for the chosen drain system. To save height, the slope was reduced to 0.5 %. Water backs up and overflows. In addition, the sealing collar of the linear drain was embedded with voids and creases, and the sealing tape in the wall corner was damaged during tiling. For months, water seeped unnoticed into the screed and insulation with every shower.

    Measures: Remove the tiles and the soaked sloped screed in the shower area completely. Dry out the floor structure with technical drying equipment. Install a flat renovation drain system (e.g. from 60 mm installation height) with sufficient drainage capacity. Lay new sloped screed at 2.0 %. Apply continuous bonded waterproofing to DIN 18534 with correctly integrated sealing collar and sealing tapes. Re-tile.

    Customer explanation (example): "During the renovation, there wasn't enough height in the floor, so the shower was built with too little slope and the water runs into the bathroom. On top of that, the waterproofing under the tiles is leaking at the drain, so for months water has been seeping unnoticed into the floor and down to the ceiling below. We need to open up the shower floor, dry out the screed and ceiling, and rebuild the shower with a special flat drain and a watertight waterproofing layer."

    Learning record

    Nothing you enter is saved. Download or print the record before you close the page.

    Simulation locked

    Simulation: section through the shower floor

    Simplified teaching model · slope exaggerated in the drawing · time-lapse: 1 s of showering ≈ 1 week of use

    Guest toilet (ground floor), ceiling from below Concrete slab Insulation Sloped screed Waste pipe Hallway Bathroom Shower area Drain Tile + waterproofing
    Drainage
    –
    Screed moisture
    –
    Screed cover above pipe
    –
    Crack risk (tiling)
    –
    Tiling / use
    –
    Time in use
    –
    Shower off.

    Sim-Bridge · Prototype v0.1 · Simplified teaching model. Manufacturers' instructions and DIN 18534 apply. The simulation prepares for work on the real component and does not replace it.

    Notes for teachers

    Learning objective

    Based on structural constraints (slab height, drain position, screed build-up), learners can plan the layers of a level-access shower correctly, dimension the required slope and the bonded waterproofing to standard, and diagnose typical installation errors and their long-term consequences.

    The "Sim-Bridge" model

    PhasePurposeTime
    1 Work orderA real customer case instead of a topic5 min
    2 PredictionMake prior knowledge and misconceptions visible. Locked before the simulation opens.5–10 min
    3 ExploreTargeted tasks: normal condition, limit value, damage with time delay, counter-check15–20 min
    4 RuleCompare prediction and findings, write own if-then rules, then model rule10 min
    5 WorkbenchWork plan and real measurements (height, slope, coating thickness, CM test). Simulation deliberately locked.45–90 min
    6 FeedbackReal measurements into the model, reflection, customer explanation15 min

    Grouping and role

    Typical misconceptions

    Guiding questions for the debrief

    Limits of the model